ELECTRIC START A 5KW GENERATOR SET AND PERFORM DURING OPERATION CHECKS
PERFORMANCE MEASURES
+(Not Scored in Sequence)
PASS
FAIL
*1.
Circuit Breaker. Place circuit breaker in the OFF position.
____
____
2.
Operating Levers and Controls. Insure that all operating levers and controls are in
the proper operating positions.
____
____
*3.
Voltage Phase Output Selector Switch, or Change Board.  Position the output
selector switch in accordance with the output voltage and phase requirement.
____
____
+ = Not scored in sequence but must be completed prior to beginning the Scored
in Sequence performance measures.
____
____
(Scored in Sequence)
*1.
Starting Instructions. Use TM 5-6115-584-12 to prepare for starting and to start
5KW generator set.
____
____
*2.
Fuel Selector Valve. Place fuel selector valve in the proper position, depending on
source of fuel.
____
____
*3.
Air Cleaner Indicator.  Should be showing green, if not, replace element or
indicator if not functional.
____
____
*4.
Master Switch. Place master switch in the proper position.
____
____
*5.
DC Control Circuit Breaker. Push DC control circuit breaker in.
____
____
*6.
Ear Protection. Ear plugs or ear headset will be in place at this time.
____
____
*7.
Make sure speed control is set properly.
____
____
*8.
Master Switch. Turn switch to prime and run.
____
____
*9.
Master Switch.  Turn switch to start position and hold until engine comes to
operating speed.
____
____
Change 3 H-46


 