Custom Search
 
  
 
TM 11-5895-1847-12&P
OPERATOR AND UNIT MAINTENANCE
LCU 2000 GLOBAL MARITIME DISTRESS AND SAFETY SYSTEM
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Personnel Required
Seaman 88K
OPERATE THE NAVIGATION INTERFACE AND SWITCHBOX
1.
Place the power switch (1) in the PWR position to receive ship's power and supply regulated power to the PLGR.
5
4
1
PWR
2
OPERATE
OFF
PROGRAM
3
BYPASS PWR
8
SW 1
SW 2
SW 3
SW 4
SW 5
SW 6
7
6
2C030-1
2.
Place the power switch (2) in the OFF position to stop power output to the PLGR from the interface and
switchbox (8).
3.
Place the power switch (3) in the BYPASS PWR position to allow the interface and switchbox (8) to receive ship's
power and supply unregulated power to the PLGR.
4.
Place the OPERATE/PROGRAM switch (4) in the OPERATE position to allow GPS data from the PLGR to be
distributed to J1 - J5 outputs.
5.
Place the OPERATE/PROGRAM switch (5) in the PROGRAM position to provide a direct programming link
between the PLGR and a data terminal.
NOTE
SW1 thru SW5 (6) are not used when the interface and switchbox (8) is installed in the
navigation location.
6.
Place SW6 (7) in the UP position to allow interface of GPS differential signal data.
END OF WORK PACKAGE
0030 00 1/2 blank


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business