TM 55-1905-223-24-18-1
Unscrew hexagon nut (12) and remove toggle switch (13).
g.
h.
Unscrew retaining ring (14) and remove stop push switch (15).
i.
Unscrew retaining ring (16) and remove start push switch (17).
Unscrew retaining ring (18) and remove run indicator (19).
j.
Repair at this level of maintenance is by replacement of indicator lights (7, 9,
and 19) push switches (11, 15 and 17), and toggle switch (13).
a.
Install run indicator light (19) and secure with retaining ring (18).
b.
Install start push switch (17). and secure with retaining ring (16).
c.
Install stop push switch (15) and secure with retaining ring (14).
d.
Install toggle switch (13) and secure with hexagon nut (12).
e.
Install tension push switch (11) and secure with retaining ring (10).
Install tension indicator light (9) and secure with retaining ring (8).
f.
Install high temp indicator light (7) and secure with retaining ring (6).
g.
h.
Connect electrical leads to run indicator (19), start push switch (17), stop
push switch (15), toggle switch (13), tension push switch (11), tension
indicator (9), and high temp indicator (7).
i.
Replace door (2) and secure with door latches (4) and screws (3, Sheet 1).
Restore power to control panel and remove tags.
j.
a.
Position control panel on bulkhead and secure-with four machine screws (2,
Sheet 1).
b.
Connect electrical power cable (3) and remove tags.
c. Restore power to control panel and remove tags.
2-562


 