Custom Search
 
  
 
TM 55-1905-223-24-3
(2)
The gasket (4) must be installed against the block with the sealing bead tow rd the cover (6).
a
(3)
Measure the gasket thickness. The new gaskets must be the same thickness as the gaskets which
were removed.
(4)
Install the gaskets (4) over the dowel pins in the block.
b.
Install the cam follower housings on the dowel pins in the block as follows:
(1)
Install the push rods (1) in the cam follower socket (2) and position cover (6).
(2)
Install six capscrews (5) in each cam follower housing (6).
(3)
Tighten the capscrews in the sequence shown in Figure 3-23to the following values.
NOTE
All capscrews are tightened to the specification in step (a); then step (b).
(a) Tighten to 15 ft-lb (20 N ) torque.
m
(b) Tighten to 35 ft-lb (45 N ) torque.
m
FIGURE 3-23. Cam Follower Housing Torque Sequence.
3-55


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business