Custom Search
 
  
 
TM 55-1905-242-14
0075 00
6
12
1
11
2
3
7
9
8
13
E
P
I
R
B
10
4
5
INSTALLATION
1.
Place the lower mast section base (13) into its mount on the aft bulkhead of the pilothouse and attach it using the mast
pivot pin (10).
2.
Attach a mooring line around the upper mast section (1) near its junction with the lower mast section (3).
3.
Lead the mooring line over the pilothouse and forward onto the accommodation module top and position two crewmembers
to work the mooring line.
4.
Using the mooring line, raise the mast to its upright position and secure it to the pilothouse top (9) using the two bolts
and nuts (8).
5.
Reconnect the navigation light wiring (4) to the mastlight connector panel (5) using the labels from step 3 of Removal as
a guide.
6.
Reconnect the leads to the GPS antenna (6) and to the digital compass unit (7) using the labels from step 4 of Removal
as a guide.
7.
Raise the upper mast section (1) to its full height and secure it with two bolts and nuts (2).
8.
Disconnect the mooring line; remove all lockouts and tagouts; energize the navigation lights, GPS, digital compass, and
loudhailer; and check the operation of all of these systems.
END OF WORK PACKAGE
0075 00-2


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business