TM 55-1905-242-14
0133 00
INSTALLATION--TANK UNIT
1.
Adjust the probes (5) on the new tank unit (3) to the same level as the old unit. Ensure that the lowest level probe is set
as an "Empty Indicator" (6) and that the middle and highest probes are set as "Full Indicators" (7).
2.
Screw the tank unit (3) into the tank (4).
3.
Connect the wiring (2) to the wiring terminals (1) using the labels from step 3 of Removal--Tank Unit as a guide.
4.
Fill the potable water tank and check for leaks at the tank unit (3).
5.
Remove the lockouts and tagouts and check the operation of the system.
6.
Install the void cover on Void 6 and terminate the confined space procedures.