TM 55-1905-242-14
UNIT MAINTENANCE
FOR LANDING CRAFT, MECHANIZED (LCM-8) (ALL VESSELS WITH MOD 2 APPLICATION)
BILGE SYSTEM PIPING, VALVES, STRAINERS, HOSES, AND FITTINGS, REPLACE
INITIAL SETUP:
Tools and Special Tools:
Personnel Required:
Tool Kit, Mechanic's Rail and Marine
One Watercraft Engineer, 88L
(Item 1, Table 1, WP 0230 00)
(Trained in Confined Space Entry)
One Entry Supervisor/Attendant
Equipment Condition:
Void prepared for confined space entry with
Materials/Parts:
Confined Space Entry Permit secured, IAW
Sealant (Tape, Antiseizing) (Item 14, Table 2, WP 0230 00)
Organizational Confined Space Entry SOP
and FM 55-502
References:
FM 55-502
Organizational Confined Space Entry SOP
TM 55-1905-242-24P (WP 0063)
REMOVAL--BILGE STRAINER
WARNING
Only properly trained personnel may enter confined spaces, or act as entry supervisors
and/or attendants for those working in confined spaces. Before entering into a confined
space, the space must be cleared for entry and a Confined Space Entry Permit must be
secured. All entry into confined spaces must be in accordance with the Organizational
Confined Space Entry Standard Operating Procedure and FM 55-502. Entry into an
uninspected confined space may result in serious injury or death.
1.
Remove the void cover from the desired void and prepare it for confined space entry in accordance with the Organiza-
tional Confined Space Entry SOP and FM 55-502.
2.
Unscrew the strainer (1) from the piping (2).
0140 00-1


 