TM 55-1905-242-14
0160 00
REMOVAL--(continued)
2.
Don protective goggles, gloves, and/or apron.
3.
Break the weld (1) that attaches the component (2) to the vessel (3) by grinding, gouging, or cutting.
4.
Remove the component (2) to be replaced.
INSTALLATION
1.
Prepare the installation area by grinding, welding, or other appropriate method.
2.
Position a new component (2) in place on the vessel (3).
! CAUTION
Improper connection of ground leads can cause serious electrolytic and electronic
damage to the vessel and its components. Always ensure that ground leads are con-
nected in accordance with TB 55-1900-204-24.
3.
Weld the component (2) in place.
4.
Chip and grind the welds as required.
5.
Prime and paint the repaired area in accordance with TB 43-0144.
6.
Remove the confined space entry permit if posted.
END OF WORK PACKAGE