Tweet |
Custom Search
|
|
|
||
TB 600-1
10.
Instructions to the Student.
a.
This performance test contains four parts.
PART I
Installing a 5KW GED or DED Generator Set.
PART II
Perform Before Operation Checks.
PART III
Electric Start a 5KW Generator Set and Perform During Operation Checks.
PART IV
Stopping a 5KW Generator Set and Perform After Operation Checks.
b.
This is a graded task requiring individual work.
c.
There are 75 performance measures in this task of which you must complete 60 to receive a GO.
d.
This test must be completed within two hours to receive a GO.
e.
Everything you will need to complete this test is
f.
If, at any time of the test there is a malfunction with the generator set, inform the Scorer.
g.
If you should receive a NO GO, you will be counseled by the Testing Control OIC or NCOIC, receive remedial training,
and be retested.
h.
After you complete the test, the scorer will critique your performance. You will assist the scorer in preparing the site for
the next student.
C.
SAFETY RESTRICTION. All safety precautions will be strictly adhered to during installation, performance of operator/crew
preventive maintenance checks, and operating the Generator Set.
Change 3 H-30
|
||