TB 600-1
B.
DIESEL ENGINE DRIVEN
TIME STARTED _____________
PART I
INSTALLING A 5KW GENERATOR SET
PERFORMANCE MEASURES
(Sequence is Scored)
PASS
FAIL
*1.
Installing. Before attempting to install the generator set, it must be completely
____
____
shut down.
(Sequence is Not Scored)
____
____
1.
Site Selection. Uses TM 5-6115-584-12 to install the 5KW generator set.
*2.
Distance to Load. Position the generator set as close as possible to the load.
____
____
*3.
Access. Provide enough clearance around the generator set to facilitate operation
____
____
and maintenance activities.
*4.
Fuel Supply. Provide an adequate supply of clean fuel to meet requirements
based on operation time.
____
____
5.
Fuel Selector Valve. Place in position depending on fuel source used.
____
____
6.
Foundation. Place the generator set on reasonably firm dry ground.
____
____
*7.
Mounting. Position the unit so that it is reasonable level and the frame is
supported on its entire bottom surface.
____
____
*8.
Power Transmission Cable.
Connect the cable to the load terminals in
accordance with the output voltage and phase requirements.
____
____
9.
Voltage Phase Selector Switch, or Change Board. Position the output selector
switch in accordance with the output voltage and phase requirement.
____
____
Change 3 H-41
|
||