a. Prior to propeller shaft and bearing maintenance the landing craft must be either
lifted from the water, or drydocked.
(1) Lifting of the landing craft.
(a)
Lifting of the landing craft can be done by either:
A 200 long ton (203 metric ton) crane.
Two 100 long ton (101.5 metric ton) cranes.
(b)
Attach lifting sling as shown-using 4-1/2 diameter pins in the deck
lifting pads.
(2) Drydocking.
Refer to Foldout (FO-8) for the Drydock plan.
(3) Docking in an LSD.
The landing craft is designed to be docked in an LSD. The height limitation is 17 feet
9 inches (5.41 m). The height is from the bottom of the keel and skegs and a projection
of that line. All items above this line are to be removed and stowed.