TM 55-1905-219-14-2
2-189. BOW RAMP - RAISING (Cont).
e. Winch Compartment.
(1) Turn mechanical brake wheel (6) clockwise to lock winch. Turn electrical brake screw (5) clockwise to engage.
(2) Install pawl (3) and pawl locking pin (4) in the engage position.
(3) Remove hand crank (7) and store.
(4) Install hand crank switch cover (1) to the high speed shaft stub (2), engaging the electrical current to the winch.
2-190. STERN GATE.
a. The stern gate can be either raised or lowered manually.
NOTE
This procedure requires two persons.
b. To raise the stern gate proceed as follows:
(1) Port Side Vehicle Deck.
(a)
Remove dog bolt (1) and clamp (2).
(b)
Remove davit (3).
2-720