Custom Search
 
  
 
TM 55-1905-220-14-11
6-1. PROPELLER SHAFT AND BEARINGS - MAINTENANCE INSTRUCTIONS
a. Prior to propeller shaft and bearing maintenance the landing craft must be either lifted from the water, or dry-
docked.
(1) Lifting of the landing craft.
(a) Lifting of the landing craft can be done by either:
o A 200 long ton (203 metric ton) crane.
o Two 100 long ton (101.5 metric ton) cranes.
(b) Attach lifting sling as shown using 4-1/2 diameter pins in the deck lifting pads.
(2) Dry-docking.
Refer to Foldout (FO-16) for the Drydock plan.
6-2


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business