a. Prior to propeller shaft and bearing maintenance the landing craft must be either lifted from the water, or dry-
docked.
(1) Lifting of the landing craft.
(a) Lifting of the landing craft can be done by either:
o A 200 long ton (203 metric ton) crane.
o Two 100 long ton (101.5 metric ton) cranes.
(b) Attach lifting sling as shown using 4-1/2 diameter pins in the deck lifting pads.
(2) Dry-docking.
Refer to Foldout (FO-16) for the Drydock plan.