2-36. SHORE POWER (Cont).
(4) The shore power available indicator (2) should be lit.
(5) The shore power phase sequence indicator (3) labeled ABC should be lit.
If CBA is lit in the shore power phase indicator (3), STOP - the
incoming wiring is reversed. Remove the shore power cable from
the source of shore power. Switch any two (2) wiring connections in
the vessel shore power connection box. When the ABC lamp is lit
proceed.
Generator must be secured before switching to shore power.
(6)
Check that generator #1 and generator #2 main circuit breakers (4 and 5) are in the OFF position.
(7)
Place the shore power circuit breaker (1) in the ON posit ion.
(8)
Place the distribution main circuit breaker (6) in the ON position.
(9)
Place the generator #2/shore power voltmeter switch (7) in the SHORE POWER position. The generator
#2/shore power voltmeter (8) should read 450V.
(10) Place the generator #2/shore power ammeter switch (9) in the SHORE POWER position. The generator
#2/shore power ammeter (10) should indicate the amperage drawn.