TM 55-1905-221-14-1
Table 2-1. Preventive Maintenance Checks and Services (Continued)
Interval
Item
Procedures
Equipment will be
Item
To Be
Reported Not Ready/
No.
Inspected
Available If:
B D A M Q BA
29
Battle
Ensure lantern works
lantern
and batteries are
in good repair.
30
Anchor light
Ensure cable, plug,
lense and jack staff
are in good repair
and functional.
31
Tools and
Ensure tools are
repair parts
accounted for on DA
Form 2062 and marked
IAW para 1.8J AR
735-5. Ensure
running spares are
protected from the
elements (Sea Water
laying in bilges
sitting on fuel
tank, etc).
SECTION III. OPERATION UNDER USUAL CONDITIONS
2-5. STARTING THE LCM.
a.
Preparation for Starting.
(1)
Perform the before-operation services (para 2-4).
(2)
Lubricate the landing craft as specified in L055-1905-221-14.
(3)
Open the two sea water seacocks (para 2-2c(11)).
(4)
Open the four sea water discharge valves (fig. 2-8) to 1/2 open positions.
(5)
Disengage the three bilge pump clutches (fig. 2-9).
(6)
Open fuel supply and return valves at each tank (fig. 2-7).
(7)
Disengage the two ramp hoist pump clutches (fig. 2-16).
(8)
Open the hydraulic suction valve (fig. 2-10).