TM 55-1905-221-14-3
6-15
RUDER AND TILLER (Continued)
LOCATION/ITEM
ACTION
REMARKS
INSTALLATION (Cont)
f.
Install studs (25),
Do not tighten.
nuts (24), and jamnuts
(23) to secure.
g. Position stuffing box
(22) and gasket (21) in
place.
h. Secure with capscrews
Do not tighten.
(20) and nuts (19).
i.
Position thrust bearing
(18) in place, then
place upper thrust
flange (17) and lower
thrust flange (16) over
bearing.
j.
Place assembled tiller
in place in vessel and
secure flange assembly
with cap screws (15),
lockwashers (14), and
flange mounting nuts
(13).
k.
Secure rudder stock
assembly to vessel with
nut (12).
l.
Align holes in nut (12)
with hole in rudder
stock and install cotter
pin (11).
m. Tighten nuts (19 and 24).
n. Install crank assembly
(10) onto rudder shaft
(30) with bolts (9),
washers (8), and nuts
(7).
6-160
|
||