d. Remove protective caps, plugs, inserts, wrappings, and tape when inspection/inventory is completed.
Inspect piping openings for damage. Wipe off dirt, grease, or protective films at time of installation.
e. Remove chocks from resilient mounted components.
4-5. Initial Setup Procedure.  Includes operational checks and inspections that are not performed for a
routine startup.  Direct support maintenance personnel will perform initial setup in accordance with the
operator's manual, TM 55-1905-223-10. Also refer to Chapter 2, Section II.
4-6. Normal Startup. Refer to the operator's manual, TM 55-1905-223-10.
4-7. Shutdown Procedure (Usual or Unusual). Refer to the operator's manual, TM 55-1905-223-10.
SECTION III. INTERMEDIATE GENERAL SUPPORT PREVENTIVE
MAINTENANCE CHECKS AND SERVICES (PMCS)
4-8. PMCS. There is no PMCS at the general support level. See Chapter 2, Section
SECTION IV. INTERMEDIATE GENERAL SUPPORT TROUBLESHOOTING
4-9. Troubleshooting . There is no troubleshooting at the general support level. See Chapter 2, Section IV
and Chapter 3, Section IV.