Custom Search
 
  
 
TM 55-1905-223-24-5
FIGURE 3-2. Lifting Fixture P/N ST-125.
WARNING
Personnel stand clear during hoisting operation.
c.
Lift the engine slowly, ensuring that the lifting device is holding properly.
d.
Remove the engine.
NOTE
It may be necessary to move, or remove, other external components or fixtures to provide necessary clearance
for removing engine.
REPLACEMENT
a.  Hoist the new engine into place on the frame support and install the mounting capscrews (2) and bolts
(1). Torque to 135 ft-lbs.
b.
Remove the lifting fixture.
c.
Connect all lines and install all couplings listed in equipment conditions.
NOTE
Replace any external components or fixtures that were moved, or removed, to facilitate removing the old
engine.
d.
Conduct break-in, pre-servicing, start-up, and engine run-in in accordance with paragraphs 2-5 through
2-9.
3-9


 


Privacy Statement - Copyright Information. - Contact Us