TM 55-1905-242-14
0026 00
CRANE (continued)
9.
To stow the crane:
a.
Rotate the crane until the boom is facing forward.
b.
BOOM UP the first boom section (78) to a near-vertical position.
c.
BOOM DOWN the second boom section (79) to its full BOOM DOWN position.
d.
BOOM DOWN the first boom section (80) to its full BOOM DOWN position.
e.
BOOM UP the second boom section (81) until it rests on the boom rest.
10. To secure the crane:
a.
Stow the crane as described in step 9 of the To Stow the Crane procedure in this work package.
b.
Secure the hydraulic system by reversing the procedures contained in steps 1.c-1.e of this procedure.
78
79
80
81
0026 00-26