Custom Search
 
  
 
TM 55-1905-242-14
0223 00
DISASSEMBLY--FIRST BOOM (continued)
1
4
2
37
3
36
26
1
2
13
36
4
3
1
24
4
2
3
25
12
16
11
5
23
22
14 15
10
9
3
21
22
27
30
29
6
28
4
20
19
2
1
8
7
31
18
33
32
35
34
17
CLEANING
1.
If not already on, don protective gloves and goggles.
2.
Clean all metal parts in cleaning solvent and dry with clean wiping rags.
3.
Dispose of all contaminated materials in accordance with local regulations.
INSPECTION
NOTE
Replace worn or damaged parts with new.
1.
Inspect both boom sections for cracks, deformities, or other damage. Replace any damaged boom section.
2.
Inspect the bushings and pins for wear. Replace any worn bushings or pins.
3.
Inspect the wear pad for wear. Replace the wear pad if it is worn.
4.
Inspect the cylinders for leaking or damage. Replace any leaking or damaged cylinder.
0223 00-3


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business