Custom Search
 
  
 
TM 55-1925-273-10-1
0079 00
a.
Press and release the STOP pushbutton(s) (figure 3, item 6).
b.
Verify that the MOTOR RUN indicator(s) (figure 3, item 5) go(es) out.
7.
Secure the piping system by placing the following valves in the CLOSED position:
a.
All valves on the ballast manifold.
b.
BB-25, BLST MANF TO PMPS OUTLT (figure 6, item 5)
c.
BB-26, B/B PMP No. 1 BLST. SUCT (figure 6, item 14), bilge/ballast pump 1 suction from ballast manifold
d.
BB-27, B/B PMP. No.2 BLST. SUCT (figure 6, item 15), bilge/ballast pump 2 suction from ballast manifold
e.
BB-33, B/B PMP. No.2 BLST TO MANF. (figure 6, item 7), bilge/ballast pump 1 discharge
f.
BB-32, B/B PMP No.2 OVBD DISCH (figure 6, item 8), bilge/ballast pump 2 discharge
g.
BB-58 (figure 6, item 12), bilge/ballast overboard discharge
FROM BALLAST TANK TO BALLAST TANK
1.
Align the piping system by placing the following valves in the OPEN position:
a.
BB-32, B/B PMP No.2 OVBD DISCH (figure 6, item 5), ballast manifold suction (from) isolation valve.
b.
BB-26, B/B PMP No. 1 BLST. SUCT (figure 6, item 14), bilge/ballast pump 1 suction from ballast manifold.
c.
BB-27, B/B PMP. No.2 BLST. SUCT (figure 6, item 15), bilge/ballast pump 2 suction from ballast manifold.
d.
BB-35, B/B PMP No. 1 BLST. TO MANF. (figure 6, item 16), bilge/ballast pump 1 discharge to ballast manifold.
e.
BB-33, B/B PMP. No.2 BLST TO MANF (figure 6, item 17), bilge/ballast pump 2 discharge to ballast manifold.
2.
At the ballast manifold perform the following actions:
a.
OPEN the suction valve for the tank to remove ballast from.
b.
OPEN the discharge valve for the tank to send ballast to.
3.
Start the pump(s) by completing the following actions at the bilge/ballast pump motor controllers 1 and/or 2:
a.
Press and release the START pushbutton(s) (figure 3, item 4).
b.
Verify that the MOTOR RUN indicator(s) (figure 3, item 5) illuminate(s).
4.
Verify that the pump discharge pressure gauge(s) read(s) about 10 to 20 PSI (.67 to 1.38 bar).
5.
Observe the tank level on the remote TLI receiver module (figure 7, item 1) of the tank being filled.
6.
When the tank reaches desired level, stop the pumps by completing the following actions at the bilge pump motor
controller(s):
a.
Press and release the STOP pushbutton(s) (figure 3, item 6).
b.
Verify that the MOTOR RUN indicator(s) (figure 3, item 5) go(es) out.