TM 55-1925-273-10-1
0081 00
4.
OPEN MSD-3 POTW FILL TO MSD ISLN (figure 3, item 6) and PW-100 POTW ISOLATION (figure 3, item 16)
valves and fill the media tank (figure 3, item 32) with potable water. Fill the media tank until the water in the wet well
(figure 3, item 33) reaches a level halfway up the wet well sight glass (figure 3, item 34).
5.
CLOSE MSD-3 POTW FILL TO MSD ISLN (figure 3, item 6) and PW-100 POTW ISOLATION (figure 3, item 16)
valves.
6.
Ensure that chlorine tablets have been installed in the chlorinator (figure 3, item 36) (TM 55-1925-284-14&P).
7.
Set to ON the MSD control panel master switch (figure 4, item 1).
8.
Press the START button (figure 4, item 2) on the MSD control panel (figure 4, item 3) to start the blower (figure 3, item 38).
9.
Set the PUMP HAND/OFF/AUTO switch (figure 4, item 4) on the MSD control panel (figure 4, item 3) to AUTO.
1
BLOWER RUN
PUMP
HAND
AUTO
OFF
START
STOP
2
5
3
4
Figure 4. MSD Control Panel
0081 00-5