Tweet |
Custom Search
|
|
|
||
TM 55-1925-273-10-1
0105 00
ROWPU FRESH WATER FLUSH
NOTE
Always perform a fresh water flush after ROWPU operations, and at least once a week when the
ROWPU is in layup.
1.
Perform the ROWPU System Shutdown procedure in this work package.
! CAUTION
If valves RO-V-1-1 and RO-V-2-1 are not CLOSED, the fresh water flush will not be effective,
and the service life of the reverse osmosis membrane elements will be shortened.
2.
CLOSE the following valves:
a.
RO-V-1-1 (figure 13, item 4), ROWPU 1 inlet sea water supply
b.
RO-V-2-1 (figure 13, item 8), ROWPU 2 inlet sea water supply
3.
OPEN the following valves:
a.
RO-V-9 (figure 17, item 1), fresh water flush pump supply
1
Bilge & Ballast Pumps
A/C/ Refrigeration
Ship's Stores
Condensing Unit
Refrigeration Condensing
Unit
Figure 17. Potable Water Valves on AMS 2 Aft Bulkhead
0105 00-15
|
||