TM 55-1925-273-10-2
0141 00
Table 1. Preventive Maintenance Checks and Services Chart (continued)
ITEM INTERVAL MAN-
ITEM TO BE
PROCEDURE
EQUIPMENT
NO.
HOUR
CHECKED OR
NOT READY/
SERVICED
AVAILABLE IF:
82
After
0.5
FIRE AND
a. Check pumps, couplings, and sea chest
Sea chest cannot be
GENERAL
valves for proper operation. Sea chest
cleared, and suction
SERVICE PUMPS
is clogged when suction pressure is
pressure cannot be
greater than 10 in Hg (254 mm Hg)
lowered below
10 in Hg
(254 mm Hg).
b. Check gauges for normal readings.
Fire main discharge
Fire main discharge pressure should
pressure above
be 60 to 120 PSI (4.1 to 8.3 bar)
120 PSI (8.3 bar)
against dead head.
or below 60 PSI
(4.1 bar).
c. General service pressure should be
Unable to maintain
greater than 60 PSI (4.1 bar) under
general service
normal operating conditions.
discharge pressure
at 60 PSI (4.1 bar)
under normal
operating conditions.
Fire and General
Service Pumps
Bilge Manifold
83
After
1.0
BILGE/BALLAST
Visually check oil level sight gauge (1/2
Pump is defective
PUMP
full). Inspect pumps, couplings for leaks,
or fails to operate.
loose connections, and damage.
Bilge/Ballast
Motor Controller
Bilge/Ballast Pump
Bilge Manifold
0141 00-21
|
||