5.
Product Water Discharge System
(a)
Pumps, Shore Discharge - Drain and blow dry with dry compressed air. Replace plugs removed to effect
(b)
Product Water Discharge Piping Tanks to pumps and pumps to reel and deck discharge. Piping will be
drained and blown dry with dry compressed air. All valves in the system will be left in the open position,
except the discharge into the shore discharge hose reel. The deck opening will have the cap installed.
6.
Drinking Water Pressure Set
(a)
Pump - Drain and blow dry with dry compressed air.
(b)
Piping - Includes fill and drain to storage tank, suction to pump, discharge to pressure tank, and distribution
from pressure tank thru-out. All piping will be drained and blown dry, with dry compressed air. All valves in
this system will be left in the open position.
NOTE
Lines will be disconnected at low points as required to effect drainage,
then reconnect, leave in a ready status.
7.
Auxiliary Equipments System
(a)
Air Compressor - Drain and fill the crankcase with P-10 grade 30. Disconnect the air discharge to tank.
Remove the intake filters. Operate the compressor during which time, spray 5 ozs. of P-10 grade 30 into the
air intake or until the oil mist is evident in the air discharge. Reconnect discharge line to tank. Clean and
reinstall air intake filters. Leave in a ready status.
(b)
Air Tank - Drain the tank. Remove plugs, open drain valve. Bag and tag plugs and secure adjacent to tank.
(c)
Air Piping - Drain, leave all valves in the open position except on the weather deck, outside D/H envelope.
NOTE
It may be desirable to use this installed system for blowing other
systems in which case processing may be delayed until near the final
stages of the preservation process.
8.
Welder- No preservation required. Ensure cable secured.
9.
Eye Wash Tanks - Drain, no other preservation required.
10.
Fuel Oil Transfer System
(a)
Piping - Drain piping back from day tank in conjunction with fuel storage tank preservation item 23.(d).
(b)
Pump, Fuel Transfer Close suction and discharge valves. Drain pump, fill with P-10 Type 1 Grade 30
preservation oil (MIL-L-21260), then drain. Reinstall plugs. Install new suction filter.
11. Bilge Pumping System
(a)
Piping - Flush entire system from all stations with fresh water, the drain and blow dry. Leave all valves in
open position except deck discharge which will also be capped.