PORTABLE FIRE PUMP (PE-250) (Continued).
b.
The following is an index to the maintenance procedures:
DESCRIPTION
PARAGRAPH
Engine Control Panel
Gage Panel
Discharge Valve
Pump
Priming Pump
Carburetor
Battery
Solenoid and Electric Starter
Engine
Retractable Starter
c.
Performance Testing.
(1)
Performance test. To perform the performance test, proceed as follows:
(a)
Operate the pump (refer to Chapter 2) at a suction lift of 16 feet (4.9m).
(b)
Verify that the pump pumps 250 gpm (946.3 lpm) at a discharge pressure of 100 psi (689.5
kPa).
(c)
Check piping, valves, and fittings for any indication of leakage.
(d)
Replace any leaking component and retest the pump.
(e)
Shut down pump.