REPLACE HOSES AND FITTINGS (Continued).
INSTALLATION
1.
INSTALL VALVES AND PIPING
2.
INSTALL HOSES AND FITTINGS.
a. Ensure hose and fittings are the proper size
and length required.
b Place socket (1) in vise as shown.
c. Dip cut end of hose (3) into hydraulic oil
for adequate lubrication.
d. Thread hose (3) counter-clockwise into socket
(1) until hose bottoms Back hose off 1/2 turn.
e. Lubricate insert thread on nipple
f. Place nipple hex (2) in vise. Screw hose and
socket (1) clockwise onto nipple until large
threads engage.
g. Position socket in vise as shown and tighten
assembly with a wrench
h. Connect other end of hose to a fitting In the
same manner.
i. Re-connect hoses and fittings to their proper
connections.
j. Bleed system for air before putting it into
operation.