(1) Pay out power cable from overhead rack up ladder to 02 stern deck.
(2) Position cable end through bottom section of hand rail.
(3) Tie one end of heaving line to cable end.
(4) Throw heaving line to dockside facilities.
(5) Remove waterproof wrapping from cable connectors.
NOTE
There is 75 feet of cable; direct attention to amount of cable remaining on the
deck. There should be a sufficient amount of cable on deck to prevent it from
paying out completely. Attach a preventer line to prevent complete cable runoff.
(6) Coordinate cable payout between on board and dockside crew.
(7) Connecting cables (FIGURE 2-222).
WARNING
Ensure electrical power is OFF at dock shore power panel prior to connecting
shore power cable.
(a) Unscrew METAL CAP (1) from base of shore power cable INPUT CONNECTOR (4).
(b) Align key way on SHORE POWER CABLE CONNECTOR (2) with key slot in shore power cable
INPUT CONNECTOR (4).
(c)
With firm upward pressure, seat SHORE CABLE CABLE CONNECTOR (2) in cable INPUT
CONNECTOR (4).
(d)
Secure SHORE POWER CABLE CONNECTOR (2) by turning LOCKING RING (3) clockwise.
Tighten with wrench.
(e) At dock shore power panel, set power switch to ON position.
b. Shifting to Shore Power.
(1) At Main Switchboard (FIGURE 2-223), ensure SHORE POWER PHASE METER (1) indicates
correct phase of shore power.
CAUTION
If shore power phase meter indicates phase of shore power is incorrect, equipment
will be damaged. Refer to unit maintenance to have shore power cable
reconnected.