MAINTENANCE OF BOW RAMP ASSEMBLY
2-12. Repair Bow Ramp Assembly
This task covers:
a. Inspection, b. Service, c. Alignment, d. Adjustment, e. Repair.
INITIAL SETUP
Tools
Equipment Condition
Tool kit, general mechanic's,
Bow ramp assembly shut down and tagged
"Out of Service - Do Not Operate".
Tool kit, measuring machinist,
Reference TM 55-1905-223-10
INSPECTION
Inspection procedures are covered in paragraph 2-9 (PMCS, Item 4).
SERVICE
Service procedures are covered in paragraph 2-5.
ALIGNMENT
Alignment procedures are covered in paragraph 2-15.
ADJUSTMENT
Adjustment procedures are covered in paragraph 2-5.
REPAIR
Repair of the bow ramp assembly at the Unit Maintenance level is limited to the actions listed in Chapter 2.