TM 55-1905-223-24-16
WARNING
Improper lifting/hoisting heavy/bulky items presents hazards to equipment and
personnel.
Never hoist equipment or cargo over personnel. Ensure proper supervision and
lifting techniques are employed at all times.
Ensure working areas are cleared of all personnel except those involved with
lifting/hoisting operations.
NOTE
Reposition any previously removed shims.
(2)
Lift winch and position winch on mounting platform and check for surface contact at all bolt pads.
CAUTION
Do not pull winch down to platform. Shim the winch properly to keep from bending
the winch frame and causing misalignment of gears or other operating mechanism.
(3)
If gaps exist between bolt pads and mounting platform, shim up to bolt pads.
(4)
Secure winch to mounting platform using fourteen 1-1/4 in. Diameter mounting machine bolts and self-locking
hexagon nuts (3, 4, FIGURE 4-1).
(5)
Torque bolts to 550 ft-lb (748 N-m).
(6)
Remove four legged sling.
NOTE
Remove protective caps/plugs from hydraulic lines prior to installation.
(7)
Connect hydraulic hose connectors (2, 6, and 7) to hydraulic lines (3, 4, and 5) on deckplate at base of
hydraulic pump assembly (1).
(8)
Operate and test stern anchor winch. Refer to paragraph 2-12.
4-12


 