Tweet |
Custom Search
|
|
|
||
TM 55-1905-223-24-3
WARNING
Ensure that all power is OFF and tagged to the coolant heater
group.
(5) Remove and tag external electrical wiring to the coolant heater group (paragraph 2-36).
NOTE
Cover all engine openings to prevent dirt and debris from entering.
(6) Disconnect and tag the turbocharger and exhaust group air piping (paragraph 2-30).
(7) Disconnect and tag the following lines from the engine:
(a) Fuel supply and tank return lines.
(b) Clean oil supply line.
(c) Dirty oil drain line at sump pump.
(d) Coolant supply, drain, and remote expansion tank vent lines.
d. Attach the lifting fixture (hoist) to the four lifting pad eyes (1, Figure 3-1) provided on th generator
e
subbase (two on each side).
e. Remove the subbase mounting nuts at the six resilient mount (2) locations
(three on each side).
WARNING
Personnel stand clear during hoisting operation.
f.
Lift the set slowly, ensuring that the lifting device is holding properly.
g. Remove the generator and subbase.
NOTE
It may be necessary to move, or remove, other external
components or fixtures to provide necessary clearance for
removing the set.
h. Remove the two bolts in each mount (2, Figure 3-2) and remove the six rubber cushioned mounts.
3-10
|
||