TM 55-1905-242-14
0026 00
FIRE MONITOR
1.
If not already running, start and warm up the diesel generator as described in the Diesel Generator Startup procedure in
2.
Ensure that the fire pump strainer (14) is clean and the fire pump seacock (15) is OPEN.
15
14
NOTE
All electrical load must be removed from the diesel generator before engaging the fire
pump clutch. Failure to do so may overload and stall the diesel generator engine.
3.
Remove all electrical load from the diesel generator by setting to OFF the circuit breakers in the 220/110 Volt distribution
box.
4.
Ensure that the forward ballast tank filling valve (16) is CLOSED.
18
16