A vessel received from storage will be inspected as specified in this work package. However, storage personnel will have
performed the depreservation operation and outfitted and operated the vessel prior to the arrival of the crew.
INSTALLATION INSTRUCTIONS
If the LCM-8 Mod 2 has been in storage, or has been transported as deck cargo aboard a transport ship, perform the
following procedures:
1.
If preservation was performed on the vessel, depreservation is detailed in TB 740-97-4.
2.
Reactivation of the vessel after movement is detailed in TB 740-97-4.
3.
Open the engine room and lazarette hatches to ventilate these spaces.
4.
Open the pilothouse windows and door and the accommodation module doors to ventilate these spaces.
5.
Connect the battery cables to the batteries (WP 0092 00).
6.
Remove the mast from the engine room, and install the mast (WP 0075 00).
7.
Remove the following equipment from the lazarette and install/stow it as appropriate:
a.
Emergency tiller.
b.
Electric horn (WP 0126 00).
c.
Stanchions, lifelines, and fittings (WP 0162 00).
d.
Navigation lights (WP 0065 00).
8.
Fill the potable water tank with potable water from an approved source.
9.
Fill both fuel tanks with diesel fuel from an approved source.
PRELIMINARY SERVICING OF EQUIPMENT AND PRELIMINARY CHECKS AND ADJUSTMENTS OF
EQUIPMENT
Perform all operator and unit PMCS up through, and including, the annual level.
END OF WORK PACKAGE