Tweet |
Custom Search
|
|
|
||
TM 55-1905-242-14
UNIT MAINTENANCE
FOR LANDING CRAFT, MECHANIZED (LCM-8) (ALL VESSELS WITH MOD 2 APPLICATION)
RUDDER ANGLE TRANSMITTER, INSPECT/ADJUST
INITIAL SETUP:
Tools and Special Tools:
Personnel Required:
Tool Kit, Mechanic's Rail and Marine (Item 1,
Two Watercraft Engineers, 88L
Table 1, WP 0230 00)
References:
Equipment Condition:
TM 55-1905-242-24P (WP 0087)
RUDDER ANGLE & TANK GAUGES circuit
breaker set to ON
INSPECT
1.
Check that the rudder clamp (1) is securely fastened to the rudder stock (2). Tighten the clamping bolts (3) as necessary.
2.
Check that the followup linkage (4) is securely fastened to the rudder clamp (1) and to the followup arm (5). Tighten the
nuts (6) and swivel block (7) as necessary.
3.
Check that the followup unit (8) is securely fastened to its mount. Tighten the mounting bolts as necessary.
4.
Visually inspect the wiring (9) and its connection to the followup unit (8) for corrosion, breaks, or other signs of damage.
If damage is found, notify direct support maintenance.
6
0153 00-1
|
||