REMOVAL--HATCHES (continued)
3.
Using two crewmembers, lift off the hatch (1).
INSTALLATION--HATCHES
1.
Position the hatch (1) on the coaming (6) and align the hinges (5).
2.
Insert the hinge pins (4).
3.
Secure the hatch (1) by screwing the nuts (2) onto the studs (3).
REMOVAL--VOID COVERS
1.
Remove the bolts (7) that secure the void cover (8) to the vessel.
2.
Remove the void cover (8) and gasket (9).
3.
Clean the gasket area on the vessel and the void cover (8).
INSTALLATION--VOID COVERS
Position the void cover (8) and gasket (9) on the vessel and secure it with the bolts (7).
END OF WORK PACKAGE