Custom Search
 
  
 
TM 55-1925-273-10-1
OPERATOR'S MANUAL
INLAND AND COASTAL LARGE TUG (LT)
OPERATION UNDER USUAL CONDITIONS
TANK LEVEL INDICATOR SYSTEM
INITIAL SETUP:
Personnel Required:
One Watercraft Engineer, 88L
OPERATION
1.
Align the electrical system:
a.
In the engine room, on the STARBOARD side, at the 120V emergency distribution panel No. 1, set the TLI
SYSTEM circuit breaker (figure 1, item 1) to ON.
b.
On the 11 channel master TLI panel in the EOS, set the ON-OFF switch (figure 2, item 1) to ON.
c.
On the 7 channel master TLI panel in the EOS, set the ON-OFF switch (figure 3, item 1) to ON.
d.
Verify that the POWER indicator for each TLI panel (figures 2 and 3, item 2) illuminates.
1
Figure 1. 120V Emergency Distribution Panel No. 1
0078 00-1


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business