TM 55-1925-273-10-1
OPERATOR'S MANUAL
INLAND AND COASTAL LARGE TUG (LT)
OPERATION UNDER USUAL CONDITIONS
WORKBOAT/CRANE
INITIAL SETUP:
Personnel Required:
References:
Two Watercraft Operators, 88K
TM 55-1945-221-14&P
One Watercraft Engineer, 88L
TM 55-1945-224-14&P
LOAD MOMENT INDICATOR (LMI) STARTUP
1.
Set to ON the CRANE LOAD circuit breaker (figure 1, item 1) on the machinery DC control distribution panel (figure 1,
item 2) in the engine room.
2
1
Figure 1. Machinery DC Control Distribution Panel
2.
The Liquid Crystal Display (LCD) panel (figure 2, item 1) on the Load Moment Indicator (LMI) receiver panel (figure 2,
item 2) will display the screens shown in figures 3-6 before operator input is required.
3.
When the main winch selected screen (figure 6) appears on the LCD panel (figure 2, item 1), select the programmed
setting by pressing and holding the MODE button (figure 2, item 3) while pressing the down arrow button (figure 2,
item 4) once. At this point there are no available options.
4.
The correct load chart in use screen (figure 7) will appear on the LCD display (figure 2, item 1). At this point there are
no available options.
5.
Accept the correct programmed load chart by pressing and holding the MODE button (figure 2, item 3) while pressing
the down arrow button (figure 2, item 4) once.
0086 00-1