TM 11-5895-1847-12&P
OPERATOR AND UNIT MAINTENANCE
LCU 2000 GLOBAL MARITIME DISTRESS AND SAFETY SYSTEM
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Personnel Required
Seaman 88K
OPERATE AUTOMATIC POWER SWITCH
1.
Place the alarm mode switch (3) in either lamp and buzzer (up) or lamp only (down) position.
1
AUTOMATIC POWER SWITCH
2
EMERGENCY
BATTERY IN USE
4
PUSH TO TEST
LAMP AND BUZZER
ALARM MODE
LAMP ONLY
3
2C040-1
2.
Check meter (2) to ensure electrical power is output to GMDSS components.
TEST AUTOMATIC POWER SWITCH
1.
Place the alarm mode switch (3) in the lamp and buzzer (up) position.
2.
Press the push to test switch (4) until the lamp (1) lights and the buzzer operates.
3.
Place the alarm mode switch (3) in the lamp only (down) position.
4.
Press the push to test switch (4) until the lamp (1) lights.