2-40. REMOTE OPERATION - GENERATOR #2.
a.
The previous procedures, preliminary adjustments and generator engine-local start must be completed prior to
performing the following:
To avoid the possibility of damage to the generator do not operate the
generating system at reduced speeds for an extended period of time with the
voltage regulator in operation.
Shore power is being fed from the switchboard to the vessel.
b.
The following procedure is for generator #2 ONLY.
(1)
Place generator 2/shore power ammeter switch (1) in the GEN 2 position.
GENERATOR #2 - REMOTE
2-279


 