Custom Search
 
  
 
TM 55-1905-223-24-18-2
(11) Position gasket (2) and flange (3) on side of frame.
(12) Install two machine screws (4) and secure gasket and flange.
(13) Install three gaskets (1) on frame top.
REPLACEMENT
a. Install vertical gear assembly as specified in paragraph 3-17 .
b. Install horizontal gear assembly as specified in paragraph 3-18 .
c. Install bowl assembly as specified in paragraph 3-16 .
d. Install motor assembly as specified in paragraph 2-17 .
e. Install double gear pump assembly as specified in paragraph 2-19 .
f. Install pump connection assembly as specified in paragraph 2-18 .
g. Install hood assembly as specified in paragraph 2-20 .
h. Fill gearbox with oil to slightly below full mark on sight glass (17). (See LO 55-1905-223-12).
i. Remove tag and turn ON electrical power at P205 power/lighting panel.


 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business