TM 55-1905-242-14
0141 00
INSTALLATION--STRAINER
1.
Clean all pipe threads with a wire brush.
2.
Wrap all male pipe threads with antiseizing sealant tape.
3.
If the nipple (3) was removed, thread the nipple into the strainer (2).
4.
Thread the strainer (2) onto the elbow (4) and tighten it snugly.
5.
Connect the hose (1) to the strainer (2).
6.
If no further components will be replaced, clear the lockouts and tagouts and return the valves to their operational
positions.
REMOVAL--PIPING, FITTINGS, HOSES, VALVES
1.
Disconnect the appropriate hose (1) or union (5) as necessary to remove the piping section that contains the piping,
hose, valve and/or fitting to be replaced.
2.
Disassemble the piping section as required to gain access to the piping, hose, valve, and/or fitting to be replaced.
INSTALLATION--PIPING, FITTINGS, HOSES, VALVES
1.
Clean all pipe threads with a wire brush.
2.
Wrap all male pipe threads with antiseizing sealant tape.
3.
Assemble the piping section with new piping, hoses, valves, and/or fittings to its original configuration.
4.
Connect the piping section back into the vessel by attaching the unions and/or hoses that were disconnected in step 1
Removal--Piping, Fittings, Hoses, Valves in this work package.
5.
Remove the lockouts and tagouts and return the valves to their operational configuration.
END OF WORK PACKAGE
0141 00-2